Planned Utilization, Remaining Utilization, and Actual Utilization from SYNCHRO 4D PRO to Control

hello, it's complicated to implement so please take your time


  1. add "Resource Utilization" in

  2. get those three sections from SYNCHRO 4D PRO into "Resource Utilization"


better yet, giving end users options to choose what to display - Physical Quantity or Resource Utilization


screenshot attached for reference