Hey,
I was testing out the Synchro Control - Power Bi plug in and ran into a little issue. Not all the information I wanted was getting exported and some data I wasn't interested in was.
Is it possible to add in a feature so we can determine which data gets imported into Power Bi when using the plug-in? Would it be possible to use the current settings of Resource tab, Gantt Chart, etc when synchronizing the data. Or save certain settings as layout and make the export based on a that. (Also allow for the export of Resource/Task Codes and Resource/Task User Field Values)
Add the ability to export Task/Resource Usage Spreadsheet, with the above mentioned comment into account.
Sincerly