Currently all Schedule Tasks within the Synchro 4D Pro .sp file are displayed in the Gantt Window accessible from Synchro Control \ Schedule.
As we can have several thousands of Activities, it will be difficult for User to understand which are the Schedule Tasks participating to the view in the 3D Window.
Therefore a functionality allowing to filter Schedule Tasks around the Time-line is required (with a customizable look-ahead period around the Time-line).
In addition it is necessary to have an option to see only the "Active" Schedule Tasks when animation is running (i.e. the ones having a Material Resource assigned).
In other word we would like to see only schedule Tasks participating to what is shown in the 3D Window.
This enhancement request is internally referred as 4DMS-20.
Thank you for your idea. Part of this idea is already released and tasks are filtered for the selected look ahead period.